Part-IS has applied since 22 February 2026. This guide shows what a small operator, ATO or CAMO actually has to put in place, using EASA's own June 2026 guideline for simple organisations. Then take the 15-question self-check and get your gap list.

Diese Seite auf Deutsch · Esta página en español

Are you in scope?

Part-IS is two regulations: Implementing Regulation (EU) 2023/203 for organisations overseen by national authorities, and Delegated Regulation (EU) 2022/1645 for design and production organisations. For operators and training organisations the one that matters is 2023/203. It applies from 22 February 2026 Art 16.

Article 2(1) lists who is in. The ones small organisations ask about:

  • Air operators under Part-ORO, except those that only fly ELA2 aircraft, or only fly single-engine aeroplanes or helicopters with 5 passenger seats or fewer, not complex, taking off and landing at the same place, VFR by day Art 2(1)(c).
  • ATOs, except those only training on ELA2 aircraft or only giving theoretical training Art 2(1)(d).
  • CAMOs and Part-145 organisations, except those working only on Part-ML aircraft Art 2(1)(a), (b).
  • Aero-medical centres and FSTD operators under Part-ORA Art 2(1)(e), (f).

DTOs are not on the list. If you run a declared training organisation and nothing else, Part-IS does not apply to you.

Declared organisations that are in scope still need an ISMS, but their manual and their changes to it do not need an approval IS.I.OR.250(b), IS.I.OR.255, as amended by Regulation (EU) 2025/2293.

What Part-IS asks for

The core is IS.I.OR.200(a): an information security management system (ISMS) that makes sure the organisation does thirteen things. In plain words:

What you needIn practice for a small organisationRule
A policyOne page on how information security can affect flight safety in your organisation. Signed by the accountable manager.200(a)(1)
Risk identification and reviewA scope (which processes, systems, data and outside interfaces could affect safety) and a risk register.200(a)(2), 205
Risk treatmentFor each risk you keep, the control that brings it down, and who owns it.200(a)(3), 210
Internal reportingA way for staff to report information security events. Can be your SMS report form.200(a)(4), 215
Detect, respond, recoverA short list of trigger events and what to do for each one.200(a)(5), 220
Authority measures and findingsA procedure to act on measures and findings your authority notifies.200(a)(6), (7), 225
External reportingReport significant incidents and vulnerabilities to the authority within 72 hours (see below).200(a)(8), 230
Contracted activitiesKnow which security tasks an IT provider does for you, and put them in the contract.200(a)(9), 235
PeopleThe accountable manager appoints someone for Part-IS compliance and someone for its compliance monitoring, with a deputy.200(a)(10), 240
RecordsRisk records, incident records and key process records kept at least 5 years.200(a)(11), 245
Compliance monitoringAudit Part-IS like the rest of your system, feedback to the accountable manager.200(a)(12)
ConfidentialityProtect information other organisations share with you, by sensitivity.200(a)(13)
Manual and changesAn information security management manual (ISMM), which may sit inside your existing manual with a cross reference, and a change procedure.200(c), 250, 255

Two points in IS.I.OR.200 help small organisations most. Point (d) says the processes "shall correspond to the nature and complexity" of your activities and "may be integrated within other existing management systems". Point (e) allows a derogation: the authority can approve you not to run an ISMS if a documented risk assessment shows your activities pose no information security risk with a potential impact on aviation safety. Reporting under Regulation (EU) 376/2014 still applies, and the approval is reviewed every oversight cycle.

Source: EASA Easy Access Rules for Information Security, revision of December 2025, and Regulation (EU) 2023/203 on EUR-Lex.

The simple-organisation route (EASA G-04, June 2026)

On 8 June 2026 the Part-IS Implementation Task Force of EASA and the national authorities issued guideline G-04, "Part-IS proportional implementation". It is written for authorities, but it says it "can be also used as guidance for those organisations". It tells inspectors what to accept from organisations that are simple from an information security point of view.

Being small is not enough on its own. G-04 uses three factors, which you agree with your authority:

  • how safety-relevant your role is (your place in the chain, the aircraft, the organisations you connect to);
  • how complex your organisation is (staff, departments, layers);
  • how complex your IT and data are (and how connected to outside parties).

What G-04 accepts from a simple organisation:

  • Short documents. Policies and procedures "can be concise, clear and easy to read". Templates are fine if tailored.
  • Key policies first: management commitment, access control and incident response.
  • Integration with the SMS. Put the information security policy inside the safety policy, use the same risk method, run internal reporting through the SMS report, and use the same auditors if they are qualified for both.
  • Start from your SMS hazard list. Ask which existing safety risks could be caused by an information security threat, then list the assets and interfaces involved.
  • A simple likelihood score. Appendix 1 scores opportunity, preparation and execution 1 to 3 each: 3 to 4 is low, 5 to 6 medium, 7 to 9 high.
  • Playbooks. A predefined list of trigger events known to staff (an application stops responding, a suspicious message arrives) with a standard response for each.
  • External reports through ECCAIRS 2, the same route you already use for safety occurrences.
  • Few KPIs. A handful of relevant ones, such as training completion rate or Part-IS findings from audits.
  • Scaled audits. Focus on the most critical areas, results to the accountable manager.
For initial approval, the authority reviews the manual ("ISMM review") against the "Present" and "Suitable" levels. Many other elements can be audited later inside normal oversight. G-04 says material for the "Operating" and "Effective" levels will come later.

Source: Part-IS TF G-04, Part-IS proportional implementation, June 2026 (PDF).

Reporting: the 72-hour rule

Under IS.I.OR.230, any information security incident or vulnerability "which may represent a significant risk to aviation safety" goes to your competent authority, and to the design approval holder if it affects an aircraft system or component. The timing IS.I.OR.230(c):

  1. Notification as soon as the condition is known to the organisation.
  2. Report as soon as possible, and within 72 hours from the time it was known, unless exceptional circumstances prevent this.
  3. Follow-up report on recovery and prevention, as soon as those actions have been identified.

This sits on top of Regulation (EU) 376/2014, not instead of it IS.I.OR.230(a). Regulation (EU) 2026/1821 also added information security items to the mandatory occurrence lists. Work out your dates with our occurrence reporting deadline calculator.

A 30-day plan for a small team

  1. Week 1: scope. Take your SMS hazard list. Mark each hazard that a hacked, wrong or unavailable system could cause: flight planning, mass and balance, tech log, crew records, email, the maintenance system. List the systems and outside parties behind each one.
  2. Week 2: risks and controls. Score likelihood with the G-04 three-question method. For every risk above your acceptance line, write the control and an owner. Fill the gaps first: access control, backups, multi-factor sign-in.
  3. Week 3: reporting and response. Add an "information security" category to your SMS report form. Write a one-page playbook list of trigger events and responses. Add Part-IS to your occurrence procedure with the 72-hour report.
  4. Week 4: manual and people. Write the policy into your safety policy, add an ISMM chapter (or a cross-referenced section), appoint the Part-IS responsible person and compliance monitoring, run a short awareness session, and add Part-IS to your audit plan.

If your risk assessment shows no safety-relevant information security risk at all, write it up and ask your authority about the IS.I.OR.200(e) derogation instead.

Free Part-IS readiness self-check

15 questions, about 5 minutes. Built on the elements EASA G-04 Table 1 asks authorities to assess at the "Present" and "Suitable" levels. Your answers stay in your browser: nothing is sent or stored.

1Have you defined the scope of your ISMS: the safety-relevant processes, systems, data and outside interfaces, with reasons for anything left out?
2Do you have a written information security policy, linked to aviation safety, with objectives, available to all staff and contractors?
3Has the accountable manager appointed a person for Part-IS compliance, a deputy, and someone for Part-IS compliance monitoring?
4Is there a documented risk process (identify, assess, treat) with clear acceptance criteria and who may accept a risk?
5Have you done an initial risk assessment covering the main threat scenarios, including those at your interfaces with other organisations?
6Do you keep an asset inventory (processes, software, hardware) and is it filled in?
7Does every risk you keep have a treatment measure, an owner and a date?
8Do you have a way to detect incidents, and a standard response and recovery for the events most likely to hit you?
9Can staff and contractors report information security events, and is it defined who evaluates them?
10Is there a procedure to decide what goes to the authority, and to report it within 72 hours, with a follow-up?
11Do you know which information security activities are contracted out, and do the contracts cover them, your oversight and authority access?
12Have you defined competence and trustworthiness for staff with Part-IS roles or access, and assessed current staff?
13Are your Part-IS records, their retention (at least 5 years) and their protection defined?
14Do you have procedures for measures and findings the authority notifies, and for protecting information other organisations share with you?
15Is the ISMM written (alone or inside your manual) with a change procedure, and is Part-IS in your compliance monitoring plan?

0 of 15 answered

Scoring: Yes 2 points, Partly 1, No or Not sure 0, out of 30. It shows where you stand against the G-04 elements. It is not an authority assessment and not legal advice.

Questions we hear

Does Part-IS apply to a DTO?

No. Declared training organisations are not on the list in Article 2(1) of Regulation (EU) 2023/203. If you also hold an AOC or an ATO approval, those parts are in.

We have four aircraft and nine staff. Is that "simple"?

Possibly, but size alone does not decide it. G-04 looks at safety relevance, organisational complexity and IT complexity, and expects you to agree the level with your authority. A small HEMS operator with a connected ops system may not be simple on the IT factor.

Can our safety manager also do Part-IS?

The rule asks the accountable manager to appoint a person or group with the right knowledge for Part-IS compliance, and someone for compliance monitoring IS.I.OR.240(b), (c). G-04 accepts combined positions in simple organisations if the responsibilities can be discharged and competence is there. For some combinations, where compliance monitoring sits with a person who also runs the activity, G-04 asks for the annual internal audit to be done by an independent auditor.

Do we report information security incidents in ECCAIRS 2?

G-04 expects simple organisations to use the external reporting route they already use for safety occurrences, ECCAIRS 2, which now has an information security taxonomy. Check the form your authority defines.

Is a derogation realistic for us?

Only if a documented risk assessment shows no information security risk with a potential impact on aviation safety, for you or for others IS.I.OR.200(e). Most operators use ops, planning or maintenance software that feeds flight safety, so expect to need a light ISMS. The risk assessment is the same work either way, so start with it.

Try it on your own data

Free 30-day pilot

Load your own findings register, audit plan and occurrence log into Folvan and see the clocks, checklists and audit pack work on real records. No card, nothing to install. We help you move the data in.

Start the free 30-day pilot
This opens your own mail app with a short note to hello@folvan.com. Nothing is stored on this page.